  • Client

    Cree Nation of Waskaganish

  • Value

    $ 7.5M

  • Project scope

    1 km pipe

  • Workforce

    Mostly from the community

Project description

  • Deforestation work, topsoil stripping
  • Complete road infrastructure and related works
  • Construction of the rain outlet with a diameter of 1 200 mm - 945 m.lin.
  • Ditch excavation and profiling - 1 900 m.lin.
  • Related work including construction of culverts and manholes
  • Project carried out in partnership with a local company
 

 

 

Partenariat

 