Waskaganish, New Rupert substation force main

  • Client

    Cree Nation of Waskaganish

  • Value

    $ 4.3M

  • Project scope

    2.6 km pipe

  • Workforce

    Mostly from the community

  • Replacing the sewage pressure line
  • Supply and installation of a 250 mm diameter PVC DR 18 discharge pipe
  • TerraBrute CR connecting the Rupert pumping station to the treatment basins - 2 600 m.lin.
  • Supply and installation of drainage chamber
  • Supply and installation of air vent chamber
  • Project carried out in partnership with a local company
 

 

 

Partenariat

 

Emerson Swallow Président

 